Dated: 23/09/2019


All 3 basements casted along with ground Floor Casted
First Floor (MLCP 1 80% Casted)
Second Floor (MLCP 2 70% Casted)
Third Floor (MLCP 3 shutting work in progress)
Plumbing & Fire fighting work Awarded