Dated: 01/12/2020


10th Floor Completed (Including 1-5 MLCP)
11th floor work in progress
Plumbing & Fire Fighting
Basement 1, 2 & 3 completed
MLCP 1, 2,3 & 4 Completed
Ground floor & MLCP 5th in progress

HVAC
Ducting work of basement 2 in progress

Electrical Works
Electrical conducting in progress

Landscape& Road work
Earth filling of landscape area in progress